Work will begin June 11 on a project that will repair and replace deteriorating water and sewer mains along North Boulevard and South Boulevard between Marion Street and Oak Park Avenue.

Plans call for water and sewer improvements on North Boulevard between Forest and Kenilworth avenues, including under the Clinton Avenue viaduct. Affected roadways also will be completely reconstructed, and North Boulevard restriped to accommodate a new bike lane from Kenilworth Avenue to Oak Park Avenue.

The South Boulevard work will include lighting improvements, sidewalk repairs and street resurfacing as well as minor sewer repairs between Marion Street and Home Avenue. 

The project will require periodic closures of both North Boulevard and South Boulevard. Project updates will be posted here as they become available. 

Note that there will be no disruptions to garbage collection dates or location during construction.

For questions related to the project, contact project engineer Andy McDonald at 630.557.6285 or amcdonald@v3co.com.

PROJECT UPDATES

October 26: North and South boulevards were set to reopen to traffic by the end of this week, as the project comes to an end. 

October 16: New street lighting was installed last week as restoration continues on North and South Boulevards. All concrete work is expected to be completed today. By the end of the week, the bottom layer of asphalt will be placed at all remaining locations on North and South Boulevards. The week of Oct. 22 will see the final surface of asphalt placed, and pavement striping and signage installed. Both streets will then be opened to traffic as the remaining punch-list work is undertaken.

October 5: Restoration continues along North and South Boulevards with the first layer of asphalt placed. Crews are also restoring the pavement beneath the Clinton and Kenilworth viaducts. The Kenilworth Viaduct will be closed to traffic starting Mon., Oct. 8 and vehicles will be detoured via Lake Street. 

September 28: Pavement removal was set to being today (Sept. 28) on South Boulevard between Marion Street and Home Avenue. The intersection of South Boulevard and Clinton Avenue was expected to remain closed to traffic through this week for site restoration following the water main construction. South Boulevard traffic continues to be rerouted at Kenilworth Avenue to Randolph Street between Kenilworth and Home avenues. New asphalt is expected to be installed on South Boulevard next week as restoration of North Boulevard continued. North Boulevard remains closed during work hours at Forest Avenue, but access to private driveways has been retained.

September 21: Initial paving has been completed along North Boulevard. While the street remains closed to through traffic, one-way travel has been restored from Forest Avenue.

Setpember 14: The intersection of South Boulevard and Clinton Avenue is expected to remain closed to traffic for another week for sewer work and site restoration. Connections are being made to the new sewer main beneath the Clinton Avenue viaduct between South and North boulevards. South Boulevard traffic continues to be rerouted at Kenilworth Avenue to Randolph Street between Kenilworth and Home avenues. Restoration of North Boulevard is expected to begin next week now that new curbs, gutters, sidewalks and driveway entrances have been installed. Although North Boulevard remains closed during work hours at Clinton Avenue, access to private driveways has been retained. Installation of catch basins continued this week on South Boulevard between Home Avenue and Marion Street, and restoration and street lighting installation is scheduled to begin next week. No street closures are required for this work, but some pay-by-space street parking will be lost during construction. 

September 7: The intersection of South Boulevard and Clinton Avenue is closed to traffic for excavation of a shaft for a new sewer connection, as well as additional boring and restoration activities. The intersection is expected to remain closed for about two weeks. Boring for a new sewer main beneath the Clinton Avenue viaduct between South and North boulevards was expected to be completed this week. South Boulevard traffic continues to be rerouted at Kenilworth Avenue to Randolph Street between Kenilworth and Home avenues, with local access to properties and parking available via temporary two-way traffic on either side of the Clinton Avenue intersection. Restoration continued on North Boulevard around areas where new curbs, gutters, sidewalks and driveway entrances have been installed.  Although North Boulevard remains closed during work hours at Clinton Avenue, access to private driveways has been retained. Installation of catch basins was expected to begin this week on South Boulevard between Home Avenue and Marion Street. No street closures are required for this work, but some pay-by-space street parking will be lost during construction. 

August 31: Boring beneath the Clinton Avenue viaduct between South and North boulevards was expected to be completed this week for installation of a new sewer main. The intersection of South Boulevard and Clinton Avenue is closed to traffic for approximately three weeks for excavation of a shaft for a new sewer connection, as well as additional boring and restoration activities. South Boulevard traffic has been rerouted at Kenilworth Avenue to Randolph Street, with local access to properties and parking available via temporary two-way traffic on either side of the Clinton Avenue intersection between Kenilworth and Home avenues.  Meanwhile on North Boulevard, restoration continued this week around areas where new curbs and gutters, sidewalks and driveway entrances had been installed. North Boulevard remains closed during work hours at Clinton Avenue, but access to private driveways has been retained. 

August 24: The intersection of South Boulevard and Clinton Avenue has been closed to traffic for approximately four weeks for excavation of a shaft for a new sewer connection. South Boulevard traffic has been re-routed at Kenilworth Avenue to Randolph Street, with local access to properties and parking available via temporary two-way traffic on either side of the Clinton Avenue intersection between Kenilworth and Home avenues. Meanwhile on North Boulevard, sewer service connections are being made and curb restoration has begun. North Boulevard remains closed during work hours at Clinton Avenue, but access to private driveways is being maintained.

August 17: The intersection of South Boulevard and Clinton Avenue will be closed to traffic for approximately four weeks beginning Monday, Aug. 20. South Boulevard traffic will be re-routed at Kenilworth Avenue to Randolph Street during the closure. Three days of sewer work is scheduled to begin next week on South Boulevard between Home Avenue and Marion Street.

August 10: Night work has been completed along South Boulevard. The work scheduled on North Boulevard for today will be completed during normal working hours. Water services for 914 North Blvd. and 100 Forest Pl. will be transferred to the new water main on Mon., August 13, 2018. Water service will be shut off during the transfer and the buildings have been notified.

August 1: The contractor will begin installing the water main between North Boulevard and South Boulevard along Clinton on Thursday, Aug. 2. During work hours North Boulevard will be closed at Clinton. Driveways will remain accessible.

July 31: The five parking spaces along North Boulevard east of Kenilworth will be blocked Wednesday, Aug. 1 in order to accommodate the installation of new watermain at Kenilworth and North Boulevard. Both north- and south-bound Kenilworth and east-bound North Blvd will be open during this time. Connections to properties will be made for both sewer and water services once the entire system has been installed. North Boulevard remains closed to through traffic between Forest and Kenilworth avenues, but is accommodating two-way local traffic. Traffic continues to be detoured around the construction site via Lake Street and arrangements have been made to accommodate affected parking permit holders’ vehicles in the Holley Court Garage.

July 20: The intersection of North Boulevard and Kenilworth Avenue will be closed temporarily to vehicle traffic next week. Connections to properties will be made for both sewer and water services once the entire system has been installed. North Boulevard remains closed to through traffic between Forest and Kenilworth avenues, but is accommodating two-way local traffic. 

July 17: Crews are installing water and sewer main between Clinton and Kenilworth this week, and the contractor expects to complete with the majority of the mainline mains this week as well. 

July 6: Installation of water and sewer mains is progressing along North Boulevard between Forest and Clinton avenues. North Boulevard remains closed to through traffic between Forest and Clinton avenues, but is accommodating two-way local traffic between Clinton and Kenilworth avenues. Traffic is being detoured around the construction site via Lake Street.

June 27: The contractor will begin installing sewer and watermain tomorrow along North Boulevard between Clinton and Forest. This will not impact resident parking this week, and residents will be notified of any private driveway closures in advance of work next week. These notices will provide the dates resident parking will be blocked and the active dates for the temporary parking passes provided.

June 7: Please note there will be no disruptions to garbage collection dates or locations during the course of construction.

June 6: Work will begin work starting Monday, June 11. Starting Monday, North Boulevard will be closed to through traffic from Forest to Clinton. Eastbound traffic will be detoured to Lake Street. Additionally, North Boulevard from Kenilworth to Clinton will be made a temporary two way street so residents can access their properties starting at Kenilworth. Also effective Monday, parking along the train tracks between Forest and Kenilworth will be removed, and permit holders will have access to parking at the Holley Court Parking Garage.